Weekly Project Updates (updated: 01/05/21)

City Projects Under Construction

Bon Air Road Bridge Replacement project 

Crews are working on rebar and falsework installation for the 4 in-creek bent caps that will eventually supprot the bridge girders. Drilling equipment will be off hauled throughout the week with periodic traffic lane closures. (more information available at www.bonairbridge.com). The project is still on schedule for completion in early 2022.

Corte Alejo (Via La Paz) Storm Drain Improvements

The Contractor is scheduled to complete extensive pavement repair on Via Barranca and complete pavement replacement on Via La Paz in mid-January, weather permitting.

Central Pathway Connector

Construction work has started on the connector path. Completion is dependent on weather and availability of concrete.


City Projects in Development

Measure B Group 3 Pavement Rehabilitation

Paving of these streets is tentatively scheduled for spring/ summer 2021. See attached project information letters send in December to all residents on affected streets (RVSD letter).

Sir Francis Drake Pavement Repair (Del Monte to Drakes Cove Road)

Paving is tentatively scheduled for spring/ summer 2021. It is likely that this work will be scheduled to occur at night and that detours will be established during those work hours.  Note that current construction work on Sir Francis Drake Boulevard is part of a separate Marin County project www.upgradethedrake.com. See project information letters sent in December to residents in vicinity of work (ESFD letter and RVSD letter)

Hillview Storm Drain Improvements

The Consultant is working on plans and specifications for construction bidding package. Pending any significant utility relocations, the new storm drains are anticipated to be installed this spring/ summer followed by paving of the streets as part of the Measure B Group 3 project.

Doherty Drive Rule 20A Utility Undergrounding

Work is progressing on acquiring several easements needed to accommodate the proposed underground utilities.  Construction is tentatively scheduled for summer 2021 pending PG&E’s final estimate of cost and acquisition of the required easements.

Magnolia ADA improvements (Ward Street to King Street)

Staff anticipates sharing survey results and reaching out to greater community with potential project components in early 2021.  Construction is tentatively scheduled for late summer 2021.